Division, aggregation, transfer and hybridisation of capacity-reservation titles under the new legislation.
Decree-Law 100/2026 introduced more dynamic management of grid-connection capacity. Capacity-reservation titles no longer operate solely as rigid blocks and can now be reorganised through several mechanisms.
A portfolio-management tool
Allocated capacity can be divided, combined, transferred or reconverted, changing how developers and investors structure renewable-project portfolios.