Environmental Impact Assessment Rules for BESS Projects

The APA has clarified when battery energy storage systems (BESS) must undergo an Environmental Impact Assessment.

Battery energy storage unit at a power plant

The Portuguese Environment Agency (APA) has clarified how the Environmental Impact Assessment (AIA) regime applies to Battery Energy Storage System (BESS) projects. Under Decree-Law No. 151-B/2013, these projects are not expressly listed in the annexes, so whether an AIA is required depends on location, size and a case-by-case assessment by the APA.

Assessment criteria

Location in sensitive areas, project size and BESS-specific risks — such as fire, release of hazardous substances or cumulative risk with other energy infrastructure — can trigger the AIA requirement. Joint Order No. 2 (APA and DGEG, 31 July 2025) further clarified how co-located storage in already-licensed renewable projects is treated.

  • Not exceeding 50 MW / 200 MWh in common areas, or 20 MW / 80 MWh in sensitive areas
  • Complying with the environmental conditions of the original DIA or DCAPE
  • Completing a post-assessment phase and keeping a 5-metre setback